CONTEXT & ISSUES

Groupe ADP adopts a 2025 Pioneers strategic roadmap to build a new airport model oriented towards sustainability and performance.

Artelia is involved in several projects contributing to this new airport model.

Performed services:

  • Project planning and control for the construction of the Air France Logistic centre, Hangar 3 & 7 (2008-2010).
  • Design in BIM, new passenger terminal building connecting Orly South and Orly West (2013-2014).
  • Master plan for the Used water network (2014).
  • Airport Safety Impact Assessment (since 2014).
  • PMC assistance for the East extension building and renovation of South Passenger terminal (2015-2016).
  • Airside dynamic modelling (2015-2017)
  • PMC assistance for the renovation and compliance of the runway 06/24 (2016-2017).
  • Technical assistance & feasibility study for the airport rainwater management (2014-2018).
  • Project planning and control for new and the extension of aircraft stands, and the renovation of 2 taxiways (2017-2018).
  • Project planning and control for West Terminal Fire Safety System Renovation (2016-2020).
  • Project planning and control for the renovation of the runway 3 (2018-2020).
  • Management, project planning and control for the ‘Orly’ Metro station, parking, roads (2016-2024).
  • Master plan for the Pressurized water network (2023-2024).
  • Project planning and control for installation of heat pumps into the geothermal power plant (2022-2025).
  • Design and construction supervision:
    – Aircraft rescue and firefighting facility (2011-2014).
    New airport transport Police building (2013-2014).
    – New VVIP building (2016-2017).
    – Waterproofing repair and reinforcement of the Bridge 2 – taxiway (road under) (2017-2019).
    – Renovation of the car park P2 & the Esplanade (2022-2026).
    – Reconfiguration of international departure process Orly 4 (2024-2027).
  • Environmental Certification HQE, ISO 14001 junction and VVIP building (2013-2019).

 

Photo credit: Direction Engineering and Capital Projects – Groupe ADP